EV Solar Diversion Hysteresis & Timer Calculator
Prevent rapid relay cycling by setting an enable delay of 60s and a disable delay of 180s. Use a hysteresis power buffer of 500-600W to ensure stable operation. Charging starts when surplus exceeds minimum charge power plus hysteresis buffer, and stops when surplus falls below minimum charge power (grid import threshold).
Interactive Parameters & Live Verdict
Rule Diagnostics & Recommendations
Engineering Formula & Verification Notes
Calculations are based on standard EVSE relay protection logic. Start threshold is defined as the sum of the minimum charging power (typically 6A * 230V = 1380W) and the hysteresis buffer to prevent immediate shutdown upon minor solar dips.
Worked Engineering Example
For a standard 7kW charger with a 6A minimum current (1380W):
- Set Enable Delay to 60s to ensure solar stability.
- Set Hysteresis to 600W to avoid relay chatter.
- Charging starts at 1980W surplus and stops at 1380W surplus.
Common Sizing & Compatibility Mistakes
Engineers often overlook the impact of rapid switching on mechanical contactors.
- Ignoring the minimum charge current of the specific EV model.
- Setting identical enable/disable timers leading to 'hunting' behavior.
- Failing to account for household base loads in the surplus calculation.
Recommended Timer Benchmarks
| Setting | Conservative | Aggressive |
|---|---|---|
| Enable Delay | 120s | 30s |
| Disable Delay | 300s | 60s |
| Hysteresis | 800W | 300W |
Frequently Asked Technical Questions
Why is a 3-minute disable delay recommended?
It provides a buffer for transient cloud cover, preventing the charger from dropping out and restarting unnecessarily.
What happens if hysteresis is too low?
The charger may cycle on and off rapidly when solar production hovers near the minimum charge threshold, causing premature relay failure.
Does this apply to all chargers?
Most smart EVSEs like OpenEVSE or evcc-compatible units use these logic principles, but check your specific firmware documentation.